Horizontal Property
Translation generated by AI. Access the original version
Demolition of works affecting common elements due to lack of community authorization
The Supreme Court (SC) has ruled in favor of an owner who was denouncing two neighbors for carrying out works in their home that were affecting common elements of the building , such as the facade and a dividing wall, and which also involved an extension of their dwelling . The key point is that these works did not have the unanimous authorization of the community of owners, as required by the Horizontal Property Law when modifying common elements and, above all, when altering the floor area and, thus, the participation coefficients. Initially, the court dismissed the lawsuit because, in its view, the works had been discussed in a meeting
of owners and their authorization had been approved by majority vote. The plaintiff did not formally challenge that agreement within the one-year deadline, so the court considered the works validated. However, the Provincial Court and now also the SC believe that this is not sufficient
However, the Provincial Court and now also the Supreme Court understand that not enough , the agreement only dealt with a modification of the facade, but the works carried out went beyond and involved an extension of the dwelling, which required unanimity. In addition, only a small part of the owners was represented at that meeting, and the plaintiff did not even vote in favor, but requested that "the Law be complied with."
The Supreme Court makes it clear that if an owner carries out works that affect common elements and increase the surface area of their house, without the permission of the entire community, any neighbor can request in court that they be forced to demolish them , even if there was an unchallenged board agreement. It is not valid for the work to have been approved by the majority if it actually required unanimity and the board only authorized something minor .
In the end, the Supreme Court confirms the judgment ordering the responsible owners to tear down the illegal construction and return the dwelling to its original state, with a deadline of 6 months to do so voluntarily before it is executed at their expense. And, in addition, these convicted individuals are ordered to pay the costs of the appeal.
Our professionals can provide you with adequate advice on the operation of your community and the adoption of agreements in accordance with regulatory requirements, as well as take appropriate action to defend your rights-
Elevator maintenance
Nullity of duration clauses and excessive notice in successive contracts This case deals with a typical contract for “preventive maintenance” of elevators, which are not fulfilled in a single day, but are provided month by month (what is called in law a successive contract). A maintenance company sued a community of owners because it decided to terminate the contract before the agreed term expired. The company claimed two things, on one hand, that unpaid invoices were paid; and, on the other, compensation for “breaking” the contract early. The conflict revolved around two clauses of the contract where one set a duration of 3 years and the other required a notice of 180 days (six months) in advance if one wanted to terminate the contract. The community argued that these conditions were abusive in the case of a consumer (in this case, the community itself). In the first instance, the court ruled in favor of the company, ordering the community to pay both the compensation for early termination and the outstanding invoices (in addition to interest and costs). However, on appeal, the Provincial Court of Málaga changed the criterion, declaring the 3-year duration clause and the 180-day notice clause null and abusive. What is the practical consequence? If those clauses are invalid, the company cannot rely on them to demand a penalty or compensation for having terminated the contract early. Nevertheless, the community must pay what it actually owed, the outstanding invoices for services already rendered. The Supreme Court confirmed this outcome, the duration and notice clauses are considered null, no compensation is due for ending the contract early, and only unpaid invoices are owed.
-
Urban leases
Does a reversible work by the tenant give the owner the right to terminate the contract?
-
Urban Leases
This website uses both its own and third-party cookies to analyze our services and navigation on our website in order to improve its contents (analytical purposes: measure visits and sources of web traffic). The legal basis is the consent of the user, except in the case of basic cookies, which are essential to navigate this website.